You probably know most of this but here goes;
-Production been shut down for a month, they haven’t laid anyone off yet as building a dam and stockpiling ore.
Mgmt afraid of lay offs as they won’t get a lot of workers back.
-Putting pressure on BC gov to issue water license. Have 6/7 miles of pipe almost ready to go to pipe in water from other lakes. Production will only be at 50% when that happens.
-Centerra has $200 million from Krygestan as a cushion. Kemess carrying on as plan. Both Kemess and Mt. Milligan Cheers mmdore shipped to MacKenzie by train for processing. That part didn’t make sense to me, maybe you could enlighten me.