Gold Production Started At Buckreef Oxide Project
VANCOUVER, British Columbia, June 17, 2020 (GLOBE NEWSWIRE) — Tanzanian Gold Corp. (TSX: TNX); (NYSE American: TRX) is pleased to announce that gold production has reached commercial level at the oxide ore processing plant at the Buckreef Project.
First bucket at the oxide open pit was on April 6, 2020. Since then oxide ore has been stockpiled at a ROM pad. Construction of the plant ended on May 28, 2020. The plant successfully completed both cold and hot commissioning and has now reached commercial production and is being operated 24/7 under two 12-hour operating shifts per day